Romanian nuclear power plant reactor refurbishment to cost EUR 1.2-1.5 bln

02 April 2018

The cost of refurbishing the first unit of the Cernavoda nuclear power plant in Romania will amount to EUR 1.2-1.5 billion, according to Nuclearelectrica general manager Cosmin Ghita.

The cost has been estimated based on the average cost of similar projects involving nuclear power plants running on the CANDU 6 technology, Ghita explained.

Nuclearelectrica’s shareholders approved the start of this project in September 2017. The refurbishing will increase the reactor’s lifecycle by 30 years. The actual work is scheduled to take place from December 2026 until December 2028, when it will be completely shut down.

The company is looking into several options for financing this project, including a loan and a bond issue. A decision on the financing will be taken during the project’s planning stage, which should end in 2021.

The Cernavoda nuclear power plant, operated by state-owned company Nuclearelectrica, has two functioning nuclear reactors with a total power of 1,400 MW. The first unit was finalized in 1996 while the second one was completed in 2007.

Romania plans to build two more reactors at Cernavoda, but the negotiations with the Chinese group selected for this project haven’t been finalized yet.

New technical problems at Romania’s Cernavoda power plant

editor@romania-insider.com

Normal

Romanian nuclear power plant reactor refurbishment to cost EUR 1.2-1.5 bln

02 April 2018

The cost of refurbishing the first unit of the Cernavoda nuclear power plant in Romania will amount to EUR 1.2-1.5 billion, according to Nuclearelectrica general manager Cosmin Ghita.

The cost has been estimated based on the average cost of similar projects involving nuclear power plants running on the CANDU 6 technology, Ghita explained.

Nuclearelectrica’s shareholders approved the start of this project in September 2017. The refurbishing will increase the reactor’s lifecycle by 30 years. The actual work is scheduled to take place from December 2026 until December 2028, when it will be completely shut down.

The company is looking into several options for financing this project, including a loan and a bond issue. A decision on the financing will be taken during the project’s planning stage, which should end in 2021.

The Cernavoda nuclear power plant, operated by state-owned company Nuclearelectrica, has two functioning nuclear reactors with a total power of 1,400 MW. The first unit was finalized in 1996 while the second one was completed in 2007.

Romania plans to build two more reactors at Cernavoda, but the negotiations with the Chinese group selected for this project haven’t been finalized yet.

New technical problems at Romania’s Cernavoda power plant

editor@romania-insider.com

Normal

facebooktwitterlinkedin

1

Romania Insider Free Newsletters