Local entrepreneurs build EUR 35 mln wind farm in Romania

05 May 2022

Two entrepreneurs in Romania’s north-eastern region of Moldova, Manole Gheorghe and Vasile Domente from Buzau, are installing wind turbines in a wind park estimated to cost EUR 38 mln in Vaslui.

East Eolian Poject, the project company owned by the two investors, obtained the technical approval for the connection a 48 MW wind farm in Vaslui to the grid.

The approval was given in early February and completes a solid portfolio of green energy projects. The portfolio of projects for which the two have already obtained technical approvals for connection to the national grid reached a value of EUR 558 mln and a total capacity of 700 MW, according to data compiled by Ziarul Financiar.

(Photo: Chernetskaya | Dreamstime.com)

andrei@romania-insider.com

Normal

Local entrepreneurs build EUR 35 mln wind farm in Romania

05 May 2022

Two entrepreneurs in Romania’s north-eastern region of Moldova, Manole Gheorghe and Vasile Domente from Buzau, are installing wind turbines in a wind park estimated to cost EUR 38 mln in Vaslui.

East Eolian Poject, the project company owned by the two investors, obtained the technical approval for the connection a 48 MW wind farm in Vaslui to the grid.

The approval was given in early February and completes a solid portfolio of green energy projects. The portfolio of projects for which the two have already obtained technical approvals for connection to the national grid reached a value of EUR 558 mln and a total capacity of 700 MW, according to data compiled by Ziarul Financiar.